Correct and accurate cost estimations are critical for shipyard companies. Traditionally cost estimations for one-off ship designs are based on expert opinions and statistical-based methods. In this paper, we introduce a method for improving cost estimations in the pre-contract s
...
A method to quantify manufacturing activities for shipbuilding projects is devised, based on extrapolation of historical projects. Extrapolation rules are based on first principles and fine-tuned using empirical data. A 4-tier hierarchical system structure is proposed, incorporat
...
Purpose
The purpose of this paper is to present a method for generating a set of feasible, optimized production schedules for the erection process of compact shipyards building complex ship types.
Design/methodology/approach
A bi-objective mathematical model is developed based on
...
Efficient planning of the section building process is important for European shipyards since delays in this process can disrupt the on-time delivery of a ship. Automatically generating production schedules of the section building process can result in higher quality schedules com
...
Automatic planning literature for shipbuilding has historically only addressed the hull-related production processes, such as section building and erection. However, the outfitting process has become increasingly important for shipyards building complex ships. Rose et al. [1] dev
...
This paper explorers the possibilities to design a ship for a future 'sea change' like a major retrofit of the engine room. In order to assess the potential future beneficial impact of such design measures, a demonstrator method has been developed that scores a concept design for
...
This paper examines the relationships constraining the different mounting tasks of the outfitting process to systematically develop task priorities. Task priorities arc selected with the goal of maximizing the controllability of the outfitting process and minimizing the potential
...
Determining the latest possible point in time during which a component can be installed is important to the efficient implementation of automatic outfitting planning methods. This point is a function of a component's size, the vessel's general arrangement, the size of the opening
...