MM

Miguel Molina-Solana

2 records found

Authored

Look-ahead planning is the stage in construction planning where information from diverse sources is integrated and plans developed for the next six/eight weeks. Poor planning of construction site activities at this stage often results in cost overruns and schedule delays. This ...

In the construction sector, complex constraints are not usually modeled in conventional scheduling and 4D building information modeling software, as they are highly dynamic and span multiple domains. The lack of embedded constraint relationships in such software means that, as ...