The Resource Constrained Project Scheduling Problem with a flexible Project Structure (RCPSP-PS) is a generalization of the Resource Constrained Project Scheduling Problem (RCPSP). In the RCPSP, the goal is to determine a minimal makespan schedule subject to precedence and resour
...
In the field of shipbuilding, there is a growing demand for faster and more efficient production processes, along with a need for swift adoption of new technologies. Modular production emerges as a potential solution, involving the development of a product family with a base plat
...
The resource constrained project scheduling problem with a flexible project structure and consumption and production of resources, involves making a selection of activities and scheduling these activities in order to minimize the makespan, subject to precedence and resource const
...
The Resource Constrained Project Scheduling Problem with a flexible Project Structure (RCPSP-PS) is a generalization of the Resource Constrained Project Scheduling Problem (RCPSP). The objective of the RCPSP-PS is to find a minimal makespan schedule subject to precedence and reso
...
The primary drivers for buying a ship from a certain yard are price, delivery time and quality. In order to decrease construction time and costs, shipbuilding companies are exploring the development of product-families to include family wide modularity and cross family standardiz
...